Saturday, March 10, 2012
Wednesday, February 29, 2012
Bass Bar
I have started on the bass bar shape and have cleats glued down (not pictured yet) to keep location of the bass bar during the fitting process.
Monday, February 27, 2012
F-holes Finished
I have been working outside of class to try to get ahead, and it is starting to pay off. As a result, my f-holes are done ahead of schedule!
Wednesday, February 22, 2012
Saturday, February 18, 2012
F-holes Started
I cut the f-holes out before the graduations were completed so that the top still had some strength while using the coping saw. I unfortunately did not get a picture of this process.
Monday, January 30, 2012
Holes Drilled for first Graduations
I used a drill press to accurately drill to 4.5 mm in the top and 6 mm in the back. This will indicate where the rough graduations will stop. After this, I will do a second drilling for the final graduations.
Monday, January 23, 2012
Finished with the Arches
It took longer that expected, but the arching is now finished.
I used a contour gauge to trace the arches to see their shape more accurately.
I used a contour gauge to trace the arches to see their shape more accurately.